City of Colorado Springs

Neutral Data Center Policies

Colorado Springs requires data center offices next to certain homes to meet Buffer 2 standards and provide one parking space per 1,000 square feet, creating limited design and parking constraints.

current law · City of Colorado Springs
Requires data center office uses in light-industrial zones to provide a specified buffer next to single- or two-family homes and one parking space per 1,000 square feet.Colorado Springs Unified Development Code § 7.3.303D.6 (Data Center Office Use)

What this means

The measure adds limited requirements for data center offices: Buffer 2 standards apply when next to certain homes, and one parking space per 1,000 square feet is required. These are modest added costs or design constraints, not a broad barrier to building or operating data centers.

People behind it

  • Approved the Unified Development Code and formally adopted it on February 14, 2023 (formally adopted at the second reading).

  • Managed the RetoolCOS zoning ordinance update (managing the RetoolCOS project).

  • Assisted the City with the RetoolCOS project (assisted by Clarion Associates).

Restrictions & requirementsHide restrictions & requirements2
  • When adjacent to attached or detached single-family or two-family dwelling zoning or uses, a data center office must meet Buffer 2 standards. The data center office buffer requirement

  • Data center office parking is required at a minimum rate of one space per 1,000 square feet of gross floor area. The data center office parking rate

Benefits & exceptionsHide benefits & exceptions2
  • The use table allows Light Industry by right in some zoning districts and through conditional-use approval in others. The code also addresses data center office uses under Light Industry standards, giving data centers a defined zoning route, subject to the district-specific rules and any applicable use-specific standards. Light Industry use-table entries and data center office standards

  • A use that existed on the UDC’s effective date and was previously permitted, but now requires conditional-use approval, is deemed to have that approval for continued operation and expansion. Expansion does not require a new conditional-use approval if it complies with applicable use-specific standards and other UDC requirements. Previously permitted uses

Sources

pending · City of Colorado Springs
Sets standards for approving data centers in Colorado Springs, including making them pay for their own infrastructure and protecting water, neighborhoods, and residents’ voice in decisions.Colorado Springs Community-First Data Center Standards

What this means

The standards would make projects more costly and could cause delays: developers would pay for needed electric infrastructure and reserved capacity, show that water is available, and sometimes fund independent studies. They do not ban data centers, so projects could still proceed if they meet the requirements.

People behind it

  • Established the data-center standards and will administer them for data-center approvals.

  • Released the COS Community-First Data Center Standards framework.

  • Will use the standards to make decisions, including considering the Project Taurus appeal.

Restrictions & requirementsHide restrictions & requirements6
  • Each proposed large-load project must demonstrate that it meets the City’s standards; the City says it will permit only data centers that do so. Meet rigorous standards

  • A data center needing major electric infrastructure must pay the full cost of new infrastructure and any capacity it reserves, even if unused, and enter long-term service agreements and provide financial guarantees. Pay the full cost of new electric infrastructure

  • Large water users must demonstrate water availability and may be required to pay for infrastructure improvements and use water-efficient technologies and conservation measures. Demonstrate water availability

  • Projects are expected to address neighborhood impacts with noise mitigation, setbacks and buffers, landscaping and screening, responsible lighting, and site design. Noise mitigation

  • When potential impacts are uncertain, particularly noise, the City may require independent technical studies before approval. Independent technical studies

  • The review process includes timely public notice, public hearings, and established Planning Commission and City Council review and appeal processes; neighborhood meetings may also be required or appropriate. Timely public notice