Cañon City
Anti-Data Center Policies
Cañon City does not specifically list data centers, so the Zoning Administrator must decide whether one fits an allowed use; if not, it is prohibited. Approval is uncertain and may require meeting site-plan and other standards.
current law · City of Cañon CityApplies general zoning and site-plan rules to data centers, but contains no data-center-specific regulations.Unified Development Code (Cañon City, Colorado)
What this means
The code does not specifically name data centers, so the Zoning Administrator would decide whether one is similar to a listed use; an unlisted use found not similar is prohibited (unlisted uses). A data center might fit a listed category such as general research facilities, but that is uncertain, and development would also need to meet applicable site-plan and other standards—creating meaningful approval risk and potential delay, with no special incentives.
People behind it
- Planning & Zoning Division
Responsible for day-to-day administration and enforcement of the Unified Development Code.
Restrictions & requirementsHide restrictions & requirements5
Data centers are not expressly listed in the use tables. The Zoning Administrator must decide whether an unlisted proposed use is substantially similar to a listed use; it is treated under that use’s rules, or is prohibited if no similar use is found. If the similar use requires conditional or special review approval, that additional approval is required.
If classified as a special review use, the data center would require City Council approval by resolution after a public hearing, following a Planning Commission recommendation. The Council may impose conditions, and the use-specific standards must also be met.
The UDC applies to land, buildings, structures, and uses throughout the City. Construction, expansion, alteration, use, or occupancy must comply with it; permits and approvals cannot be issued without compliance, and approvals issued in violation are void.
Site plan review is required before a building permit for new development, including new buildings or building expansions, and for development subject to off-street parking or loading rules. An approved site plan becomes void if a building permit is not obtained within 12 months, unless an extension is granted for good cause.
Applications must include the City Council-established fee, and the applicant is responsible for all application-review costs. Incomplete applications or applications without required fees are not processed until deficiencies are corrected.
Benefits & exceptionsHide benefits & exceptions5
Planned development offers a route for projects to use innovative designs and depart from some standard use or bulk rules. Major planned developments are for sites of at least 20 acres; minor planned developments are for smaller sites and may receive deviations from underlying district standards. Approval requires meeting review criteria, including plan alignment, compatibility, and public-welfare standards, and requires City Council action. The process allows flexibility.
An administrative exception can allow up to a 10% reduction in interior-side or rear setbacks, or up to a 10% increase in building height, subject to stated criteria. It cannot approve a use otherwise disallowed, and exceptions are barred in certain districts and for setbacks of five feet or less. The allowed setback and height adjustments.
A variance can provide limited relief from UDC requirements where strict application creates exceptional practical difficulty or undue hardship unique to the property. It requires Board of Adjustment findings, including that the relief is the minimum needed; it cannot authorize a use not permitted in the district. Relief is available for qualifying hardship.
Once an application is certified complete, it is reviewed under the procedures, standards, and fees then in effect. Later-adopted amendments generally do not apply to pending applications, unless the applicant and City agree in writing to use the revised process or the application is abandoned. Pending applications are protected from later amendments.
An approved site-specific development plan can establish vested rights for three years; a longer initial period or extension may be granted if the City finds it serves the public interest and welfare. Vested rights may be forfeited if approval conditions are not met. The three-year vesting period.