City of Arvada

This restriction takes precedence for the map color while in effect.

Neutral Data Center Policies

Arvada bars data centers within 300 feet of residential zoning districts and has enacted an 18-month pause on applications and pre-submittal activity for primary-use centers. Existing operations and some smaller accessory facilities are excluded.

current law · City of Arvada
Prohibits data centers from being located within 300 feet of a residential zoning district.Arvada Land Development Code (2020), as amended — data center definition and 300-foot residential zoning district setback (including LDC §§ 3-1-3-9.C and applicable data-center use provisions)

What this means

The measure adds a limited siting restriction: data centers cannot be located within 300 feet of a residential zoning district. That may rule out some sites, but the source does not show a general ban or other major data-center-specific burdens.

Restrictions & requirementsHide restrictions & requirements1
  • Data centers may not be located within 300 feet of the boundary of a residential zoning district; the provision states no exception. “not be located within 300 feet”

Sources

current law · City of Arvada
Prohibits Arvada from accepting applications for primary-use data centers requiring at least 10 megawatts of power for up to 18 months, or until the city adopts data-center rules.Ordinance CB26-029 — 18-month moratorium on applications for primary-use data centers

What this means

The measure would block applications and related pre-submittal activity for primary-use data centers for 18 months, making new construction and application-dependent expansions substantially harder (18-month moratorium). It would not ban operating existing centers, and some smaller, accessory facilities are excluded, but the temporary pause is a major development restriction.

Timing

Ends
18 months from the ordinance’s effective date, or when appropriate definitions, standards, and conditions are adopted into the Arvada Municipal Code, whichever occurs first

City Council may extend the moratorium by ordinance if needed.

People behind it

  • Named presenter for the ordinance; the Arvada team recommends approving the measure.

  • Named presenter and Assistant City Attorney who reviewed the ordinance; the Arvada team recommends approving the measure.

  • Introduced and ordered publication of the ordinance, and later approved the moratorium.

Show 1 more peopleShow fewer people
  • Responsible under the ordinance for administering the moratorium and conducting the public engagement process.

Restrictions & requirementsHide restrictions & requirements1
  • The City may not accept applications or conduct pre-submittal activities—including planning, building, or engineering permit processes—for a primary-use data center with projected load requirements of 10 megawatts or more. The moratorium lasts 18 months from its effective date or until relevant definitions, standards, and conditions are adopted, whichever comes first; Council may extend it by ordinance. It takes effect five days after publication following final passage. Facilities under 10 megawatts are excluded when the Director determines their computing infrastructure is accessory and incidental to the property’s primary use. Moratorium and time limit Exception

Benefits & exceptionsHide benefits & exceptions2
  • The moratorium does not apply to facilities or portions of facilities with projected loads under 10 megawatts when the Director determines their computing infrastructure is accessory and incidental to the property's primary use. The ordinance gives hospitals, telecommunications carrier facilities, internet service provider facilities, and ancillary server rooms as examples.

  • The moratorium is limited to 18 months from its effective date, or until relevant definitions, standards, and conditions are adopted, whichever comes first. Council may extend it only by ordinance.