City of Alamosa

This restriction takes precedence for the map color while in effect.

Neutral Data Center Policies

Alamosa has enacted a temporary block on permit applications to build or expand covered large-load data centers through July 31, 2027, unless the council ends it sooner. It does not explicitly restrict existing facilities.

Rating from Alamosa County as there are no scored current or future laws outside temporary restrictions for City of Alamosa.

current law · City of Alamosa
Bars the City of Alamosa from accepting applications for large-load data centers with peak electricity demand over 200 kW until July 31, 2027, unless the moratorium ends earlier.City of Alamosa Ordinance No. 20-2026

What this means

The measure would temporarily block applications for permits to build or expand covered large-load data centers until July 31, 2027, a substantial but time-limited barrier (no applications shall be accepted). It does not explicitly ban operating existing data centers, and the moratorium can end sooner if Council lifts it or adopts regulations (through July 31, 2027).

Timing

Ends
Jul 31, 2027

The moratorium ends on this date unless Council lifts it sooner or adoption of regulations governing these uses makes it moot.

People behind it

  • Introduced the ordinance and adopted it after a public hearing.

  • Directed to prepare information for the Planning Commission and/or Council during the moratorium.

Restrictions & requirementsHide restrictions & requirements1
  • Establishes a moratorium through July 31, 2027, unless Council lifts it sooner or regulations make it moot. During that period, the City will not accept for review zoning, site-development, building-permit, or other development-permit applications for large-load data centers. The definition covers facilities with peak electricity demand greater than 200 kW, individually or in aggregate. No applications pertaining to zoning peak electricity demand greater than 200 kW

Benefits & exceptionsHide benefits & exceptions2
  • The moratorium covers only facilities meeting the ordinance’s definition of a “large load data center,” including a peak electricity demand greater than 200 kW, measured individually or in aggregate. Facilities that do not meet the definition are outside this moratorium’s scope. peak electricity demand greater than 200 kW

  • The moratorium is temporary: it runs through July 31, 2027, unless Council lifts it earlier or regulations make it moot. After it ends, this moratorium no longer prevents applications, though other applicable rules may still apply. through July 31, 2027