Loading map…

City of Vernon

Neutral Data Center Policies

Vernon allows data centers without a special-use permit, but certain large increases in water use still need permits, and on-site power generation is limited.

current law · City of Vernon
Allows data centers as a permitted use in Vernon’s General Industry zone, subject to the zone’s general standards.Ordinance 1851 (Vernon Zoning Ordinance amendment; data-center regulations under consideration)

What this means

Data centers are permitted as of right, so they can avoid a special-use permit, which modestly favors building and expansion. However, general rules still apply, including a permit requirement for certain large increases in water use and limits on on-site power generation, so the benefit is limited.

Restrictions & requirementsHide restrictions & requirements17
  • Water use may not increase by more than 500 acre-feet from the prior calendar year without a Conditional Use Permit. The 500-acre-foot limit

  • Distributed generation requires a Conditional Use Permit, except solar photovoltaic generation of up to 1 MW per lot and emergency generators used only for backup when utility service is interrupted. The distributed-generation rule and exceptions

  • Upon a change of use or another event that triggers compliance, vibration from businesses on a lot may not exceed 0.04 inches per second particle velocity at the lot line without a Conditional Use Permit. The vibration limit

  • Upon a change of use or another event that triggers compliance, exterior noise limits apply cumulatively: lots within one-tenth mile of a residence or school are limited to 60 dBA from 10 p.m. to 7 a.m. and 65 dBA from 7 a.m. to 10 p.m.; other lots are limited to 75 dBA at any time. Exceeding the applicable standards requires a Conditional Use Permit. The noise limits and permit requirement

  • Storage of hazardous, flammable, or explosive materials must have safety and fire-suppression equipment meeting Vernon Fire Department requirements. Storage or activity involving acutely hazardous materials above the State Fire Code exempt amount is barred within 500 feet of a K–12 school property line. Fire and hazardous-material restrictions

  • Radioactive materials are limited to specified measuring, gauging, calibration, and tracer uses unless the City Council gives prior approval for a specific use; the code also sets a radiation limit at lot lines. Radioactive-material limits

  • Electrical and electronic equipment must be wired, shielded, and controlled so it does not adversely affect other equipment beyond the lot line; radio, television, and other telecommunications transmitters must operate at assigned wavelengths. The equipment and transmitter requirements

  • Outdoor storage and activities are subject to containment and screening rules. Materials, products, and inoperative equipment generally must be hidden from the street behind screening no higher than 10 feet; a lot with outdoor storage that abuts an existing residential use or residential-zoned lot must provide a minimum six-foot screening wall. Outdoor use may not displace required fire access, parking, loading, or maneuvering space, subject to the stated approval exception for parking reductions. Outdoor storage conditions

  • The total gross floor area of buildings on a lot may not exceed a floor-area ratio of 2:1. The FAR cap

  • Buildings and structures generally must be set back at least 21 feet from the curb face shown on the Master Plan of Streets. The General Manager of Public Utilities may approve a reduced setback, but not one that encroaches beyond the planned ultimate right-of-way. The building setback rule

  • Street-facing ancillary structures have separate setback rules: structures at least 20 feet high generally must be set back 21 feet from the curb face, while shorter structures must respect the planned ultimate right-of-way and may never be closer than eight feet from the curb. Ancillary-structure setbacks

  • Buildings and ancillary structures may not encroach into a street’s planned future ultimate width, except as otherwise provided by the code’s encroachment rules. The no-encroachment rule

  • Where parking, loading, or maneuvering areas adjoin a street, the frontage must have a qualifying barrier—such as an eight-foot wrought-iron fence, a 30-inch masonry or concrete wall, or a four-foot landscaped area—or an approved equivalent, with specified protective devices at certain driveways. Street-frontage barrier requirements

  • A new lot for a use in the I Zone generally must be at least one acre and meet the subdivision requirements; this minimum does not apply in the C-1 and C-2 Overlay Zones. The minimum-lot-size rule and exceptions

  • Off-street parking and loading facilities must comply with Chapter 17.56. The parking and loading requirement

  • Trash disposal areas must be enclosed on three sides with two block walls and one lockable gate; the walls and gate must be at least six feet high, and the gate at least eight feet wide. Trash-enclosure specifications

  • Landscaped areas, including contiguous planted areas in the public right-of-way, must be kept free of weeds, overgrown vegetation, and debris, and dead, diseased, damaged, or decaying plant materials must be removed. Vehicles parked or stopped on a lot may not extend into the right-of-way. Maintenance and vehicle restrictions

Benefits & exceptionsHide benefits & exceptions4
  • Data centers are permitted as of right in the General Industry (I) Zone, so they do not require a Conditional Use Permit under this chapter solely to establish that use. “Data centers”

  • A data center may have ancillary offices and showrooms on the same lot without a separate use permit, provided the data center remains the majority use and the ancillary use is solely connected to it. Ancillary uses may occupy no more than 20% of the gross floor area occupied by the permitted use; outdoor storage and activities are excluded. “Ancillary Use”

  • Related offices, design areas, and showrooms may also qualify as incidental uses on the same lot, provided the data center remains the majority use. Incidental uses cannot include retail or outdoor storage and activities, and the combined area for incidental and ancillary uses cannot exceed 50% of the gross floor area occupied by the permitted use. “Incidental use includes offices”

  • Ancillary retail related to a data center’s permitted use may be allowed with a Minor Conditional Use Permit. It must be on the same lot, have sufficient parking, be used solely by the permitted-use operator, and sell only products manufactured onsite or imported and stored in bulk as part of the permitted use; the combined ancillary-use area limit is 20% of the permitted use’s gross floor area. “Ancillary Retail Use”

Sources

Cookie preferences · Report missing data