Tehama County

Neutral Data Center Policies

Tehama County’s zoning rules cover occupancy of travel trailers and recreational vehicles, not data-center construction or operation, so they have no meaningful effect on data-center projects.

current law · Unincorporated areas
Does not specifically regulate data centers; it requires permits and sets conditions for using travel trailers or recreational vehicles as temporary residences.Tehama County Code, Title 17 (Zoning)

What this means

The measure governs occupancy of travel trailers and recreational vehicles, not building or operating data centers. It therefore has no meaningful effect on data center projects.

People behind it

  • Enacted and adopted the ordinance adding Chapter 17.86 to the Tehama County Code.

  • Administers the temporary occupancy permit process for travel trailers and recreational vehicles.

  • Makes permit determinations and may extend, suspend, or revoke temporary occupancy permits under the ordinance.

Sources

Specific to Tehama County only.

pending · County measure
Recommends requiring data centers in the M-1 Light Industrial district to obtain a conditional use permit rather than allowing them automatically.Tehama County Rezone 26-03 (2026)

What this means

The proposal would change data centers in the M-1 district from a permitted use to a use requiring a conditional use permit. That adds an approval step that could bring extra costs and delays, but it is not a ban; the document does not describe added operating rules.

People behind it

  • Proposed changing data centers from a permitted use to a use requiring a conditional use permit and prepared the rezone materials.

  • Directed staff to pursue the zoning change and is the body asked to adopt the CEQA findings and approve Rezone 26-03.

  • Responsible for conducting the public hearing and recommending the CEQA findings and rezone approval to the Board of Supervisors.

Restrictions & requirementsHide restrictions & requirements1
  • Data centers in the M-1 Light Industrial District would be changed from a permitted use to a use requiring a conditional use permit, adding an additional discretionary approval before they can be built, expanded, or operated.