Santa Barbara County
This restriction takes precedence while in effect. The rating below excludes temporary restrictions.
Neutral Data Center Policies
Santa Barbara County’s rules may add permit review and require adequate water, roads, and code compliance for projects in the unincorporated Coastal Zone and Montecito. The sources do not identify data-center-specific restrictions or benefits.
Incentives
Fee waivers
Affordable Housing overlay-zone projects may receive discretionary County development-fee waivers, reductions, or deferrals, with savings passed to residents through lower rents or purchase prices (fee relief). This is a housing benefit, not a data-center incentive.
current law · County measure: Montecito Community Plan AreaRequires any data center in the Montecito plan area to follow the development code and obtain applicable permits; this section sets no data-center-specific rules.Santa Barbara County Code, Chapter 35 (Zoning)
What this means
The measure does not specifically promote or prohibit data centers, but it requires new uses and construction in the Montecito plan area to comply with the Development Code and says building and grading permits cannot be issued otherwise (new uses and structures must comply). That could add some permitting work, but the source does not say whether data centers are allowed in particular zones or what standards would apply.
People behind it
- Santa Barbara County Board of Supervisors
Adopted the Development Code and is responsible for its administration.
- Montecito Planning Commission
Responsible body for administering the Development Code.
- Montecito Board of Architectural Review
Responsible body for administering the Development Code.
Show 2 more peopleShow fewer people
- Director of the Santa Barbara County Planning and Development Department
Responsible for directing and administering the Development Code.
- Santa Barbara County Planning and Development Department
Department responsible for administering the Development Code under the Director's direction.
Restrictions & requirementsHide restrictions & requirements5
The Montecito Development Code applies to all land uses, subdivisions, and development within the Montecito Community Plan Area. Establishing, constructing, reconstructing, altering, replacing, or operating a data center would therefore require compliance with the applicable Development Code provisions.
The County may not issue a Building Permit or Grading Permit unless the proposed construction complies with all applicable provisions of the Development Code.
An existing data center or other land use remains lawful only if it is operated and maintained in compliance with all applicable Development Code provisions, including the rules governing nonconforming uses, structures, and lots.
If requirements conflict, the most restrictive requirement generally controls, unless the Code provides otherwise. However, an applicable Development Agreement or Specific Plan controls over conflicting Development Code standards.
Compliance with the Development Code does not eliminate the need for other County permits or permits, approvals, or entitlements required by a special district, other agency, or state or federal regulations.
Sources
current law · County measure: Montecito Community Plan AreaRequires data centers built or operated in Montecito to comply with the applicable development rules and obtain required permits; it does not set data-center-specific rules.Santa Barbara County Montecito Land Use and Development Code
What this means
The code generally applies to land uses and development in Montecito, but the amendments focus on child care, day care centers, and EV charging—not data centers (applies to all land uses and development). The sources identify no data-center-specific benefits or added restrictions, so they do not indicate a meaningful net effect.
People behind it
- Santa Barbara County Board of Supervisors
Adopted Ordinances 5167, 5168, and 5169 amending the County, Coastal, and Montecito land use codes.
- Santa Barbara County Planning Commission
Recommended the ordinance amendments concerning childcare facilities and related land-use-code revisions.
- Montecito Planning Commission
Recommended the Montecito Land Use and Development Code amendments.
Show 2 more peopleShow fewer people
- Santa Barbara County Planning and Development Department
Identified as the department responsible for administering the Montecito Development Code.
- Director of the Santa Barbara County Planning and Development Department
Identified as the official responsible for directing administration of the Montecito Development Code.
Restrictions & requirementsHide restrictions & requirements8
Within the Montecito Community Plan Area, all land uses, subdivisions, and development—including a data center—are subject to the Montecito Development Code. The Development Code applies to all land uses, subdivisions, and development.
Establishing, constructing, reconstructing, altering, or replacing a land use or structure is unlawful unless it complies with the Development Code. The County may not issue a Building Permit or Grading Permit unless the proposed construction complies with all applicable code provisions. It shall be unlawful ... to establish, construct, reconstruct, alter, or replace any use of land or structure.
An existing data-center use is lawful only if it is operated and maintained in compliance with all applicable Development Code provisions, including the rules for nonconforming uses, structures, and lots. An existing land use is lawful and not in violation ... only when operated and maintained in compliance.
A project under construction is exempt from later or amended requirements only if construction was lawfully begun before the effective date of the Development Code or amendment; otherwise, new requirements may apply. A project that is under construction on the effective date.
A data-center subdivision must meet the minimum lot-area and lot-width requirements of the applicable Montecito zoning provisions, unless a variance or another authorized exception applies, and must satisfy the County’s subdivision regulations and other applicable requirements. Any subdivision of land proposed within the County.
If the Development Code conflicts with another County requirement, the most restrictive requirement controls unless the code expressly provides otherwise. The most restrictive shall control.
A development agreement or applicable specific plan prevails over conflicting Development Code standards, so a data-center project may be subject to those separately adopted standards instead. The requirements of the Development Agreement or Specific Plan shall apply.
Compliance with the Montecito Development Code does not eliminate the need for other County permits or permits, approvals, or entitlements required by a special district, another agency, or state or federal regulations. Nothing in this Development Code eliminates the need for obtaining any other permits required.
Sources
current law · Unincorporated areas, including MontecitoDoes not specifically regulate data centers; it updates zoning rules for housing, telecommunications facilities, and certain permitted uses.Santa Barbara County Ordinance 5230 (2025)
People behind it
- Board of Supervisors of the County of Santa Barbara
Passed, approved, and adopted Ordinances 5230 through 5236.
- Mona Miyasato
Clerk of the Board responsible for maintaining the ordinances and making them available for public inspection and copying.
- Sheila de la Guerra
Deputy Clerk who signed the ordinance certification on behalf of the Clerk of the Board.
Sources
current law · Unincorporated areas, including areas within the Orcutt, Summerland, and Toro Canyon plan areas and outside the Montecito Community Plan areaRequires data centers to meet the county’s zoning, permit, environmental, utility, and safety rules, but sets no standards specifically for data centers.Santa Barbara County Land Use and Development Code
People behind it
- Santa Barbara County Board of Supervisors
Adopted the Development Code and administers it as the Board.
- Santa Barbara County Planning Commission
Administers the Development Code as the Commission.
- County Boards of Architectural Review
Administer the Development Code through the County's Central, North, and South County Boards of Architectural Review.
Show 3 more peopleShow fewer people
- County Zoning Administrator
Administers the Development Code as the Zoning Administrator.
- Director of the Planning and Development Department
Administers the Development Code as the Director and has authority to interpret its provisions.
- Santa Barbara County Planning and Development Department
Administers and implements the Development Code under the direction and control of the Director.
Restrictions & requirementsHide restrictions & requirements36
Data centers are not expressly listed as allowable uses. An unlisted data center is prohibited unless the County determines it is similar and compatible with permitted uses, and that determination is available only in specified zones, including C-1, C-2, C-3, CH, CN, CS, M-1, M-RP, OT-R/GC, OT-R/LC, PI, PU, REC, SC, and TC.
A Use Determination for an unlisted data center requires a finding that it is similar to permitted uses and will not be more harmful to neighborhood health, safety, or welfare. The process includes a noticed public hearing.
Before construction, alteration, or operation begins, all required planning permits and approvals must be obtained. Building and grading permits cannot be issued unless the proposal complies with the Development Code.
Data-center development in the Coastal Zone generally requires a Coastal Development Permit, subject to exemptions for qualifying repairs and maintenance that do not enlarge the development, certain utility connections, and projects within the Coastal Commission's original permit jurisdiction.
Development Plan approval is required for all development, including grading, in zones such as M-RP, M-1, M-2, MU, PU, REC, and TC. In other zones, approval is triggered by thresholds including 5,000 square feet in some commercial zones and 20,000 square feet in many agricultural, residential, and resource-protection zones.
A Development Plan is required before a Zoning Clearance for a structure of at least 20,000 square feet, or an addition that brings a structure to at least 20,000 square feet, when the structure is not otherwise subject to a discretionary permit.
Design Review is mandatory for structures and structural alterations in several zones, including CN, C-1, C-2, C-3, inland CH, M-RP, M-1, and M-2, and may also be required in other zones or overlay areas.
A Zoning Clearance cannot be issued for a structure requiring Design Review until final Design Review approval is obtained.
Applications for Development Plans and other discretionary approvals are subject to County environmental review under CEQA, which may require additional studies and processing.
Discretionary projects may require noticed public hearings. Filing an appeal stays issuance of the permit or approval until final action, unless an exception applies.
Approval requires adequate public or private services and resources, including water, sewer, and roads. Applicants must pay for required service extensions or improvements, and inadequate services may justify denial or reduced project density.
The County may require financial assurances, including cash, a bond, a trust fund, or an irrevocable letter of credit, to guarantee completion of permit conditions. The security remains in effect until the conditions are completed.
Planning permits and related reviews carry application-processing, inspection, and enforcement fees. Unpermitted development that is later permitted is subject to an additional penalty processing fee.
A Zoning Clearance expires two years after issuance if the approved use or structure has not been established or commenced, unless extended. After a planning permit expires, work cannot continue until a new planning permit and any required building or County permits are obtained.
Development must comply with approved permit conditions and the Development Code. The County may stop conflicting work, revoke certain permits, seek injunctions or abatement, recover administrative costs, and impose civil penalties of up to $25,000 per day for willful violations.
Every use, including a change or expansion of a use or structure, must continuously maintain required off-street parking and loading. The use cannot begin and the structure cannot be occupied until required improvements are completed. Loading spaces are required for qualifying commercial buildings beginning at 3,000 square feet and industrial buildings beginning at 10,000 square feet.
Specified projects must provide stormwater controls, including commercial development of at least 0.5 acre, parking lots of at least 5,000 square feet or 25 spaces, and new development or redevelopment exceeding one acre.
Where required, landscape plans must be prepared by a landscape professional, and approval generally requires a signed landscape agreement and performance security guaranteeing installation and maintenance.
Exterior lighting must be hooded, and unobstructed beams cannot be directed toward residentially zoned or developed areas or interfere with vehicular traffic. In specified areas, lighting within 100 feet of residences, designated open space, or biologically sensitive areas must be directed away, with hoods and low-intensity decorative lighting required where applicable.
Industrial operations must comply with zone-specific performance limits. M-RP uses cannot exceed 50 decibels at or beyond the lot boundary, while M-1 and M-2 uses are subject to noise limits and restrictions on injurious odors, fumes, gases, liquids, heat, glare, radiation, smoke, dust, and vibration.
Development in an overlay zone must comply with the primary-zone requirements and additional overlay requirements, which may impose additional permits, environmental review, height limits, setbacks, habitat protections, flood review, or growth-management restrictions.
In the Summerland Community Plan area, applicable building, grading, landscaping, and other plans for new or altered buildings require Board of Architectural Review approval. A grading or development permit cannot be issued until final approval is obtained.
In Summerland, structures are limited to 22 feet in Urban Areas and 16 feet in Rural Areas, with no exemptions from those maximum heights. Commercial projects are generally limited to a 0.29 floor-area ratio and mixed-use projects to 0.35, subject to further reductions for excessive plate heights or understories.
Before discretionary approval of new development, the applicant must identify required sewage collection, conveyance, treatment, and disposal facilities. A sanitation-district can-and-will-serve letter is required for final-map recordation or land-use clearance, and the necessary facilities must be operational before final inspection.
Commercial and industrial development that contributes grease, oils, or chemicals to wastewater flows must install onsite filtration, such as charcoal filters or another method approved by the Laguna County Sanitation District.
Before discretionary action on new development, the applicant must provide an acceptable water-supply letter or demonstrate adequate long-term water supply, including projected demand, drought service, reliability, firm supplies, contracts, delivery facilities, capacity, funding, and implementation scheduling. A final can-and-will-serve letter and contracts are required before map recordation or land-use clearance.
Commercial and industrial rooftop mechanical equipment must be minimized and, where unavoidable, shielded from surrounding roadways and residences through architectural design, camouflage housing, or other methods.
In Summerland, new development must contribute its fair share of Master Drainage Plan improvement costs. Projects in the Special Problems Area require Special Problems Committee review and a finding that they will not worsen existing drainage problems, and projects causing offsite drainage impacts must provide an approved onsite drainage system.
In Toro Canyon, non-agricultural structures are subject to Board of Architectural Review criteria, including a maximum 25-foot residential height limit, limits on understories and retaining walls, non-reflective materials and colors, shielded downward-directed lighting, and a maximum 16-foot total vertical height for graded slopes and visible retaining walls, subject to limited exemptions.
In Toro Canyon, construction activities and equipment maintenance within 1,600 feet of a residence are limited to 8:00 a.m. to 5:00 p.m., Monday through Friday. Stationary construction equipment that could exceed 65 dB(A) at the site boundary must be shielded and located at least 200 feet from sensitive receptors.
Toro Canyon construction sites must provide recycling bins, collect recyclable materials accepted by County facilities, and provide adequate accessible storage areas or enclosures.
Development in or adjacent to designated Environmentally Sensitive Habitat must include mandatory buffers, including generally 100 feet from riparian forest corridors in Rural Areas, 50 feet from monarch butterfly habitat, 100 feet from wetlands, and specified buffers from oak forest, coastal sage, and scrub oak habitats.
In Toro Canyon inland areas, development is generally prohibited on slopes greater than 30 percent unless necessary to prevent denial of reasonable use. Development on slopes between 20 and 30 percent requires a qualified professional's finding that it will not cause unstable slopes or severe erosion.
Development in Toro Canyon floodways is prohibited except when it complies with applicable flood-control laws and policies. Development in the floodplains of Toro, Picay, Garrapata, or Arroyo Paredon Creeks is also prohibited unless necessary to allow reasonable use of the property or accomplish an approved major public policy goal, with additional mitigation requirements.
In Toro Canyon, subdivisions of five or more lots generally require two routes of ingress and egress for emergency access, unless the applicable fire district waives or modifies the requirement and documents its findings. Private roads and driveways must meet applicable fire-district width standards.
Before issuing a permit for a project in a potentially archaeological area, the County may require the applicant to fund a Phase I archaeological survey, and all report recommendations, including additional studies or project redesign, must be implemented.
Benefits & exceptionsHide benefits & exceptions26
Unlisted data-center uses may be approved as similar and compatible uses in specified commercial, industrial, institutional, utility, recreation, and transportation zones, allowing them to follow the processing and standards applicable to comparable listed uses.
The code permits infrastructure that can support data centers, including electrical substations, transmission lines, utility service lines, public utility facilities, water systems, wastewater systems, reservoirs, and related facilities. Approval requirements vary by zone and facility size.
Certain inland utility installations, including poles, wires, underground gas pipelines under 12 inches in diameter, similar public utility installations, specified water-well work, and certain onsite wastewater systems, are exempt from planning permits, although building or grading permits may still be required.
Industrial Research Park, Light Industry, and General Industry zones provide development pathways for industrial, research, development, office, warehouse, and utility-related uses. Development generally requires a Final Development Plan before development or grading, and structures and alterations require Design Review.
For rezoning to Industrial Research Park, Light Industry, or General Industry zones, an applicant may generally submit a Preliminary Development Plan, unless waived, allowing zoning and coordinated project planning to be processed together.
A Development Agreement may lock in a project's duration, permitted uses, development intensity, maximum height and size, and public-purpose land provisions. It may also establish later approval terms that cannot prevent development consistent with the agreement, set construction deadlines, and allow the applicant to finance necessary public facilities and later receive reimbursement. Required hearings, consistency findings, and annual good-faith compliance review still apply.
A Specific Plan allows more precise area planning, mixed uses, comprehensive site planning, and maximum flexibility in site planning, subject to environmental review, public hearings, and adoption by ordinance.
Approved planning permits run with the land, so their conditions continue to apply to successors after a change in ownership.
Lawfully established existing uses generally are not subject retroactively to later Development Code requirements. A project lawfully under construction when a code amendment takes effect generally need not be changed to meet the new requirements, subject to nonconforming-use rules.
If the Development Code conflicts with an applicable Development Agreement or Specific Plan, the standards in the Development Agreement or Specific Plan control.
Land Use Permits are decided by the Director and generally do not require the public-hearing procedure used for Conditional Use Permits. The permit remains valid for two years if the approved use or structure has not commenced, unless extended.
Development Plans within the Director's jurisdiction do not require a public hearing; notice of the pending decision must instead be given at least 10 days before the decision.
A Modification may adjust standards for an otherwise permitted use that is not subject to a Conditional Use Permit or Development Plan, including reducing setbacks by up to 20 percent, increasing height limits by up to 10 percent, increasing floor-area ratio by up to 10 percent in specified circumstances, and changing or reducing parking requirements. It cannot authorize a prohibited use and remains subject to minimum setback and parking limits.
When a Conditional Use Permit is required, the review authority may modify specified standards, including setbacks, landscaping, parking, screening, structure coverage, height, and yard areas, when justified and consistent with the Comprehensive Plan and applicable regulations.
Commercial telecommunications facilities in nonresidential zones have tiered permitting: smaller facilities may use a Coastal Development Permit or Land Use Permit, tenant improvements may use a Director-approved Development Plan, and larger facilities may use a Minor Conditional Use Permit or Conditional Use Permit.
Certain telecommunications antennas and underground equipment may occupy setback areas or rights-of-way if they do not obstruct sidewalks, trails, or vehicle access. Existing roads and driveways must be used for access where required.
Telecommunications facilities generally must be collocated on existing support structures, but separate facilities are allowed when reasonable efforts to find an existing structure fail, no nearby facility exists, or collocation would cause greater visual impacts.
Cogeneration facilities may be allowed in the M-2 industrial zone through a Development Plan and in the M-CR coastal-related industrial zone through a Land Use Permit. A Conditional Use Permit is additionally required when the facility is within 1,000 feet of another zone, and noise mitigation requirements apply.
For cogeneration facilities within 1,000 feet of an occupied residence, operations must be designed to achieve an outside nighttime noise level of 50 dB(A) at the affected residence.
Minor changes to an approved Coastal Development Permit, Land Use Permit, or issued Zoning Clearance may be approved by the Director without additional public notice when they substantially conform to the approval, do not change the use or development scope, do not alter compliance conclusions or findings, and the permit has not expired.
Minor changes to an approved Conditional Use Permit or Final Development Plan may be authorized through a Substantial Conformity Determination without public notice or a public hearing if they remain substantially consistent with the original approval. Any required follow-up Coastal Development or Land Use Permit must still be obtained before the changed development or use begins.
An amendment to an approved Conditional Use Permit or Final Development Plan that is not in substantial conformity may be decided by the Director without a public hearing, with at least 10 days' notice, if it concerns an area previously analyzed or eligible for the specified environmental review path, remains consistent with the original findings, and has substantially the same or lesser environmental impacts.
The Director may extend a Zoning Clearance, Land Use Permit, Modification, or Development Plan once for 12 additional months for good cause, subject to applicable findings and filing requirements. A Conditional Use Permit or Minor Conditional Use Permit may also receive one good-cause extension if its original approval findings remain valid.
A Variance may provide relief from strict Development Code requirements when exceptional property conditions create practical difficulties or unnecessary hardship. It cannot authorize an otherwise prohibited use, waive procedures, or reduce certain specified parking requirements.
A Zoning Clearance certifies that a compliant use or development satisfies applicable Development Code provisions and existing permit conditions. Required prior approvals and site-compliance requirements must be met.
The County may amend the Development Code to add or modify allowed uses, standards, requirements, or procedures, and may amend the Zoning Map to rezone property or add or remove overlay zones. Applicants may initiate qualifying amendments subject to ownership or substantial-interest requirements, environmental review, public hearings, and consistency findings.
Sources
Specific to Santa Barbara County only.
current law · Unincorporated coastal areasRequires data centers in Santa Barbara County’s coastal zone to comply with local zoning rules and obtain any required coastal permits.Santa Barbara County Coastal Zoning Ordinance, Article II, Chapter 35
What this means
Most of the measures do not meaningfully change data center rules. In the unincorporated Coastal Zone, projects may face added permit review and need to show that services like water and roads are adequate, creating some extra cost or delay in that limited area.
Timing
Ordinance No. 5302 is an interim urgency ordinance prohibiting the establishment, expansion, or relocation of firearm and ammunition retail sales uses. Its expiration date or ending condition is not stated.
People behind it
- Santa Barbara County Board of Supervisors
Proposed, considered, introduced, passed, approved, adopted, and directed implementation of the ordinance amendments.
- Planning and Development Department
Submitted and administered the ordinance amendment package, prepared the proposed amendments, and transmitted the adopted amendments for review.
- Lisa Plowman
As Director of Planning and Development, submitted and signed the Board agenda letter for the ordinance amendments.
Restrictions & requirementsHide restrictions & requirements20
Data-center development in the unincorporated Coastal Zone generally must comply with the Coastal Zoning Ordinance; exemptions are limited to federal land, certain state-regulated energy facilities, state universities or colleges, and specified public-agency repair and maintenance. (development within the Coastal Zone
A Coastal Development Permit is required for development, including structures, grading, utility facilities, and changes in the intensity of land use, unless an exemption or other approval applies. (change in the density or intensity of use)
A data center must be an allowed use in its base zoning district. If it is not expressly listed, the Planning Commission may have to determine that it is similar to a permitted use; conditional uses require a Conditional Use Permit and are appealable developments. (use determination)
Overlay districts impose additional requirements, and the more restrictive rule controls. Environmentally Sensitive Habitat Area regulations control over both base-zone and other-overlay regulations. (the provisions which are most restrictive shall govern)
Before issuing a Coastal Development Permit, the County must find that adequate water, sewer, roads, and other public or private services and resources are available. Applicants must pay for required service extensions or improvements, and inadequate services may support denial or reduced density. (adequate public or private services and resources)
New development dependent on private wells may be blocked when a groundwater basin's safe yield is exceeded and the project would increase water demand, subject to exceptions for legally entitled water rights and at least one single-family residence on each existing lawful parcel. (safe yield)
In rural areas, above-ground structures generally may not be placed on undisturbed slopes exceeding 40 percent, except for necessary utility lines and agricultural fences. (undisturbed slopes exceeding 40 percent)
Projects in Environmentally Sensitive Habitat Area overlays must provide additional biological, wetland, stream, grading, paving, and coverage information. Potentially adverse projects may require environmental review and inspection by a qualified biologist, and projects with significant unavoidable habitat impacts may be referred to the Planning Commission for a noticed public hearing. (applications for a Coastal Development Permit)
Environmentally Sensitive Habitat Area rules generally require a natural 100-foot wetland buffer and presumptive stream buffers of 100 feet in rural areas and 50 feet in urban areas. Structures are generally prohibited within stream corridors, except for specified facilities such as trails, necessary dams, certain flood-control works, and habitat improvements. (a buffer strip, a minimum of 100 feet)
Applicable zoning districts impose mandatory site-development limits, including setbacks, maximum building heights, lot-coverage limits, landscaping requirements, and parking requirements. For example, the R-1/E-1 district limits structures to 25 feet, while some commercial and industrial districts require development plans or impose coverage and landscaping limits. (No building or structure shall exceed a height of 25 feet)
Required parking must be continuously maintained and may not be eliminated, reduced, or converted without equivalent County-approved facilities. Parking generally must be provided on-site or within 500 feet for nonresidential uses, and the Planning Commission may require additional parking. (shall thereafter be eliminated, reduced, or converted)
Commercial buildings of 3,000 square feet or more must provide at least one off-street loading space, and industrial buildings beginning at 10,000 square feet must provide one or more loading spaces. (3,000 or more square feet gross floor area)
In districts requiring a Development Plan, permits for development, including grading, cannot be issued until an approved Final Development Plan is in place. Some districts also require a Preliminary Development Plan as part of a rezoning application. (No permits for development including grading shall be issued except in conformance with an approved Final Development Plan)
For projects subject to CEQA, the County must determine within 30 calendar days whether the application is complete; an incomplete application requires the applicant to provide information specified by the Director.
If requested information is not provided within 90 days after the County's incompleteness letter, the application expires and is deemed withdrawn. The Director may grant only one additional 90-day extension; afterward, a new complete application and fees are required.
Even after an application is accepted as complete, the Director may require additional information needed for environmental review under CEQA.
The Director may refer an application to affected or interested County departments or public agencies, and referrals are mandatory when required by the Development Code or state or federal law.
Applicants must allow County staff involved in reviewing the application to access the subject property at all reasonable times.
In the Summerland Community Plan Overlay, commercial-only development is limited to a net floor area calculated using a 0.27 floor-area ratio, while mixed-use development is limited to a 0.33 floor-area ratio.
Non-residential uses are prohibited on any lot created through an urban lot split under the SB 9 process, which would bar a data center from operating on such a lot.
Benefits & exceptionsHide benefits & exceptions6
The M-RP Industrial Research Park district allows research, development, and testing laboratories, storage warehouses, wholesale distribution, administrative offices, business headquarters, and accessory structures, potentially accommodating data-center facilities. Projects must meet development-plan and Coastal Development Permit requirements, a one-acre minimum lot size, a 35-foot height limit, a 35-percent building-and-structure coverage limit, and a 30-percent landscaping requirement.
The PU Public Works Utilities and Private Service Facilities district allows utility operating bases and service centers, central water-production and treatment facilities serving at least 200 connections, central sewage-treatment facilities serving at least 200 connections, and major electrical transmission substations, supporting utility infrastructure for large-scale industrial or technology uses. Facilities remain subject to a Final Development Plan, Coastal Development Permit, performance standards, setbacks, height limits, and landscaping requirements.
Required parking for nonresidential uses may be located within 500 feet of the main building or site, measured along streets rather than alleys, subject to applicable parking standards and any more specific zoning-district requirements.
For commercial or industrial buildings that require loading facilities, off-street loading is required only at specified floor-area thresholds, and loading spaces may be designed separately from required front and side yards if they do not interfere with circulation or parking.
Parking requirements may be modified through a Conditional Use Permit, Development Plan, or modification procedure, subject to the applicable approval process; the authority does not automatically waive the requirements.
For projects subject to CEQA, the County must notify the applicant within 30 calendar days whether the application is complete or identify missing information. After the Director finds an application incomplete for a second or later time, the applicant may appeal that determination, subject to the ordinance's information-submittal deadlines.