Florence town rezoned 1,619 acres for industrial use and approved an amendment supporting data-center development, but individual building plans still require review.

current law · Town of Florence, Dobson Farms development areas
Authorizes data centers at Florence Tech Park by changing the site’s land-use designation to industrial and allowing data center buildings up to 85 feet tall.Ordinance No. 769-25, Series 2025 (Dobson Farms Planned Unit Development amendment)

What this means

The measure would strongly enable data-center development by rezoning 1,619 acres for industrial use and approving the Florence Tech Park amendment (the three areas cover 1,619 acres). It does not itself approve every building: detailed plans still need review, and the sources describe no financial incentives or protections against future restrictions.

Restrictions & requirementsHide restrictions & requirements3
  • The Florence Tech Park amendment caps data-center building height at 85 feet. The taller height accommodates data centers.

  • Before each phase advances, developers must submit detailed plans for review by the Town Engineer and Planning and Zoning Commission. Detailed plans will be reviewed as each phase advances.

  • Developers committed to major road-widening and signal improvements along Attaway, Judd, and Arizona Farms roads; traffic studies will determine needed turn lanes and signals. Developers committed to constructing major widening and signal improvements.

Benefits & exceptionsHide benefits & exceptions2
  • Ordinances 766-25, 767-25, and 768-25 changed the land-use designation of approximately 239, 600, and 780 acres, respectively, from Suburban Neighborhood to Industrial, making the three areas available for industrial development including data centers. The ordinances approved the change to the Industrial Place Type.

  • The Florence Tech Park PUD amendment permits data centers and related uses, including energy production and storage, and allows data-center buildings up to 85 feet tall (compared with 60 feet for light industrial uses). Detailed site planning remains subject to later review. The amendment allows data centers up to 85 feet.