Strongly Pro-Data Center Policies

Cordova approved a loan of up to $17 million to help finance one data center project; the description identifies no new restrictions on data center development or operation.

current law · City of Cordova
Approves a five-year, up to $17 million term loan to Greensparc Alaska LLC to finance equipment for a 256-GPU edge data center in Cordova, Alaska, including high-powered computing servers, under AIDEA Resolution G25-03.AIDEA Resolution G25-03

What this means

The measure approves a loan of up to $17 million to help build a data center in Cordova, substantially easing financing for that project. The benefit is significant but project-specific, and the sources identify no new restrictions on data center development or operation.

People behind it

  • Proposed and approved the $17 million loan resolution and is responsible for administering the financing.

  • AIDEA Executive Director who recommended the financing and was authorized to negotiate, execute, and administer the loan documents.

  • AIDEA Vice-Chair who made the motion to approve Resolution G25-03.

Show 3 more peopleShow fewer people
  • AIDEA Board member who seconded the motion to approve Resolution G25-03.

  • AIDEA Chief Investment Officer who explained the Greensparc loan.

  • AIDEA Deputy Director introduced to answer additional questions about the financing.

Benefits & exceptionsHide benefits & exceptions4
  • AIDEA approved a loan of up to $17.0 million to finance the development and deployment of edge data-center infrastructure in Cordova, including the purchase and installation of high-powered computing servers.

  • The approved financing is structured as a five-year, fully amortizing loan at 10% interest, with the financed equipment and cabinet serving as collateral; execution is subject to conditions including signed agreements, insurance, and customer commitments.

  • The project is supported by access to an existing Cordova Electric Cooperative facility through a ground lease and approximately 3 MW of electricity from the cooperative's Humpback Creek hydroelectric facility, allowing the data center to operate using surplus or stranded hydropower.

  • The resolution authorizes AIDEA's Executive Director to negotiate, finalize, execute, and deliver the necessary agreements and other documents, and to approve appropriate additional terms, revisions, conditions, and financing needed to implement the loan.